WINTERSHALL | Nahkla (Libya)
Project:
New GRE Water Injection
Place
Nahkla , Libya
Client
Wintershall / Future Pipe Industries B.V.
End user
Wintershall
System
Water injection line
GFI Supervised the installation of a 12.500 meter long water injection line during the Water Injection Project Phase II
in Nahkla (Libya) The working pressure of the line is 40 bar, the line was successfully tested at 60 bar.